Regulation
Country-level legal bases for data-centre waste-heat utilisation. This chapter maps Directive (EU) 2023/1791 and Commission Delegated Regulation (EU) 2024/1364 to the national transpositions in Germany, France, the Netherlands, Ireland, Italy, Spain and the Nordics. For each Member State it names the act, the competent authority, the thresholds and the applicable deadlines.
1. EU baseline
Two legal acts provide the common floor: the recast Energy Efficiency Directive (EU) 2023/1791 and Commission Delegated Regulation (EU) 2024/1364 of 14 March 2024.
1.1 Directive (EU) 2023/1791 (EED)
Article 12 obliges Member States to require data centres with an installed IT power demand of 500 kilowatts or more to file annual reports against a common European template. Article 26 establishes a general obligation to use waste heat in heating and cooling networks and sets an annual increase of 2.2 percentage points of renewable energy and unavoidable waste heat through 2030. The transposition deadline was 11 October 2025.
1.2 Delegated Regulation (EU) 2024/1364
The regulation operationalises Article 12. Annexes I and II contain the binding reporting schema for floor area, IT load, energy consumption by source, renewable share, water usage, battery capacity, waste heat reused and grid service contribution. The measurement basis is the Energy Reuse Factor under CEN/CENELEC EN 50600-4-6. The first submission cycle was 15 September 2024, subsequent cycles annually by 15 May.
2. National transpositions
The sections below summarise the state of transposition in the Member States covered by Ardor. Status tags reflect the platform's coverage level, not the legislative status of each country.
🇩🇪Germany
LiveLegal basis
| Act | Energy Efficiency Act (EnEfG), in force since 18 November 2023 |
| Sections | §§ 11, 12, 16, 17 EnEfG |
| EU basis | Transposition of Directive (EU) 2023/1791 and Commission Delegated Regulation (EU) 2024/1364 |
Competent authority
Federal Office for Economic Affairs and Export Control (BAFA), Referat 511 (Federal Agency for Energy Efficiency, BfEE), Eschborn
Reporting threshold
Data centres with an installed IT power demand of 300 kW or more (§ 13 EnEfG). Additional obligations apply from 500 kW (§ 17 EnEfG).
Reuse obligation
Data centres of 1 MW and above: Energy Reuse Factor (ERF) of 10 % from 1 July 2026, 15 % from 1 July 2027, 20 % from 1 July 2028. Evidence via the Data-Centre Register and the Waste Heat Platform.
Deadlines
Annual report by 31 March of the following year. Initial submission to the Waste Heat Platform was 1 January 2024; first ERF verification by 31 March 2027.
Platform
Rechenzentren-Register (BAFA) + Plattform für Abwärme (BfEE). As of January 2025: 2,668 companies, 19,065 waste-heat potentials, 160 TWh/yr aggregated.
🇫🇷France
Port in preparationLegal basis
| Act | Loi n° 2025-391 du 30 avril 2025 (DDADUE) |
| Decree | Décret n° 2025-1382 du 29 décembre 2025 |
| Codification | Article L.236-2 of the Code de l'énergie |
Competent authority
Direction générale de l'énergie et du climat (DGEC), Ministère de la Transition écologique
Reporting threshold
Data centres of 500 kW IT load and above. Annual public disclosure of floor area, energy consumption, installed power, waste-heat utilisation.
Reuse obligation
Data centres of 1 MW and above must valorise waste heat via a heating or cooling network, meet the 0.20 numerical indicator, or document a cost-benefit exemption.
Deadlines
First submission was 15 May 2024; compliance deadline was 11 October 2025. Subsequent reporting annually by 15 May.
Platform
National submission to DGEC, complemented by the EU database per Annex II of Delegated Regulation 2024/1364.
🇳🇱Netherlands
Port in preparationLegal basis
| Implementation | Transposition of Directive (EU) 2023/1791 via RVO reporting |
| Framework | Omgevingswet (Environment Act, 2024) |
| Measures | Erkende Maatregelenlijst (Recognised Energy-Saving Measures List) |
Competent authority
Rijksdienst voor Ondernemend Nederland (RVO)
Reporting threshold
Data centres of 500 kW IT load and above (EU baseline). Additional investigation obligation from 50,000 kWh/yr electricity or 25,000 m³/yr gas.
Reuse obligation
Data centres of 1 MW and above: waste-heat utilisation or documented exemption (EU baseline per Art. 26 EED).
Deadlines
Annual submission by 15 May. A standalone data-centre act is not yet published; regulatory pressure has risen since the Leitmotiv audit in 2026 (104 of ~160 facilities submitted, several hyperscalers filed blank forms).
Platform
RVO portal feeding into the EU database.
🇮🇪Ireland
GroundworkLegal basis
| EED transposition | In preparation via the Interdepartmental Working Group |
| Regulation | CRU decision, December 2025 |
| Grid rules | EirGrid and ESB Networks rules by end-March 2026 |
Competent authority
Commission for Regulation of Utilities (CRU); Sustainable Energy Authority of Ireland (SEAI) for monitoring
Reporting threshold
Data centres of 500 kW IT load and above (EU baseline).
Reuse obligation
New data centres must supply electricity back to the grid after six years and source 80 % of consumption from renewables. Waste-heat utilisation is secondary given limited district-heating infrastructure; exemption on grounds of technical infeasibility is the default.
Deadlines
Annual EED submission from 15 May 2026. CRU implementation rules expected by end-March 2026.
Platform
gov.ie and SEAI monitoring.
🇮🇹Italy
HoldLegal basis
| Status | 11 October 2025 transposition deadline missed |
| Draft | Legislative decree in public consultation |
| Adjacent | Decreto Energia 2025 |
| Management system | ISO 50001 mandatory for companies above 85 TJ/yr from 11 October 2027 |
Competent authority
Expected: MASE (Ministero dell'Ambiente e della Sicurezza Energetica) and GSE (Gestore dei Servizi Energetici)
Reporting threshold
Data centres of 500 kW IT load and above from 15 May 2026 (EU baseline).
Reuse obligation
Data centres of 1 MW and above (EU baseline per Art. 26 EED).
Deadlines
Annual EED submission from 15 May 2026. National deadlines track the legislative decree.
Platform
EU database via MASE/GSE (expected).
🇪🇸Spain
HoldLegal basis
| Status | Draft Real Decreto in public consultation since 15 September 2025; draft published 16 December 2025 |
| Requirements | PUE below 1.2, NIS2 cybersecurity, mandatory emissions reporting |
Competent authority
Ministerio para la Transición Ecológica y el Reto Demográfico (MITECO)
Reporting threshold
Data centres of 500 kW IT load and above (EU baseline).
Reuse obligation
Data centres of 1 MW and above (EU baseline per Art. 26 EED). Spanish requirements stricter than the EU baseline.
Deadlines
With adoption of the Real Decreto, expected Q2–Q3 2026.
Platform
MITECO portal, feeding into the EU database.
🇸🇪🇩🇰🇫🇮Nordics (Sweden, Denmark, Finland)
HoldLegal basis
| Transposition | Directive (EU) 2023/1791 via national energy agencies |
| Context | District heating widespread; waste-heat recovery already practised voluntarily at scale |
Competent authority
Energimyndigheten (SE), Energistyrelsen (DK), Energiavirasto (FI)
Reporting threshold
Data centres of 500 kW IT load and above (EU baseline).
Reuse obligation
Data centres of 1 MW and above (EU baseline per Art. 26 EED).
Deadlines
Annual EED submission from 15 May 2026 for the 2025 reporting year.
Platform
National energy agencies feeding into the EU database.
3. Non-EU sites
Norway and Switzerland are carried on the Ardor platform under bilateral recognition but are not bound by the EED. The United Kingdom is not bound post-Brexit either; ESOS and an emerging Energy Security Bill apply there. For these countries Ardor maintains facility data in the marketplace but does not produce EU-conformant compliance reports.
4. Deadline calendar
| Date | Event |
|---|---|
| 2024-09-15 | First EU-wide submission under Del. Reg. 2024/1364 |
| 2025-05-15 | Second EU-wide annual submission (reporting year 2024) |
| 2025-10-11 | EED 2023/1791 transposition deadline (France: compliance deadline) |
| 2026-05-15 | Annual submission (reporting year 2025); first mandatory cycle for Italy and the Nordics |
| 2026-07-01 | Start of the 10 % ERF quota for new-build German data centres ≥ 1 MW (§ 11 EnEfG) |
| 2027-03-31 | First ERF verification by BAFA for Germany |
| 2027-05-15 | Annual submission (reporting year 2026) |
| 2027-07-01 | German ERF quota rises to 15 % |
| 2028-07-01 | German ERF quota rises to 20 % |
5. Further reading
- Methodology: calculation model, data sources and verification procedure.
- WHC white paper: discussion paper on the European Waste Heat Certificate.
- Directive (EU) 2023/1791 (EUR-Lex).
- Commission Delegated Regulation (EU) 2024/1364 (EUR-Lex).
- EnEfG (gesetze-im-internet.de).